Rough-in Progress
The new framing is up. It is now a 2 bedroom house. The third bedroom is now a larger master bed and bath with a walk in closet. All new electric service and plumbing are now roughed in. We also have 2 new zones of central heat and air. By
Here we go…
We now have the new plans and the city permit. We are ready to go. Demolition will begin this week and I'm hoping for a 14 week finish date. I have kitchen plans being drawn now and so many ideas for this house. I will keep the true mid-century modern
Tree Removal
I had many dead trees that didn't make it through last summers drought. Three pine trees were over 100 feet tall and some others that had been neglected for years that had to come out.
Getting Started!
Peter and I have been working on the new drawings, trying to figure out how to enlarge the master bath and closet to today's standards. I'm getting bids from subcontractors and hope to apply for the building permit soon!